A week into a 3-week Sprint, a team discovered that they were unlikely to complete the Sprint deliverables. Some of the team members felt they could catch up with the work during the last 2 weeks if they got lucky with some of the dependencies. The Scrum Master is required to log a weekly Sprint status with the stakeholders. What is the most appropriate status for the Scrum Master to represent?
Early into the planning of a release, a team felt they could not demonstrate any working system in the first three Sprints because the user interface would not be built until the fourth Sprint. What should the Scrum coach of the team recommend?
During a Scrum retrospective, a team identified a bunch of improvement actions, but said they could not work on any of those because the next few Sprints were going to be very busy. How should the Scrum Master respond?
What does osmotic communication, one of the core properties of projects in the Crystal methodology, mean?
DSDM Atern proposes a prioritization scheme abbreviated as MoSCoW-Must, Should, Could, and Won’t. What is the shortest timebox for which this principle can be applied to for the identification of critical activities?
A team is working on the development of internal tools. One of the tools is meant to help optimize network traffic for the company. What is the best time to involve the transition manager from the Network Team into the team’s development cycle?
A Product Owner is going on vacation for 3 weeks and has requested the Scrum Master to stand in for her in the interim. How should the Scrum Master respond?
A team member is stuck on a technical blocking issue for the past three days. There is nobody on the team (or the entire organization) who has worked on the platform. What is the best course of action for the Scrum Master?
The new members of the team have been struggling with the core logic for a product, which resulted in quality issues in the previous Sprint. The Scrum Master managed to convince Mike, a senior technical lead, that he should spend some time explaining the logic and pair program to the new members. How should the Scrum Master proceed from this point?
A team has a very pushy and demanding Product Owner. The Scrum Master was sick during one of the Sprint planning meetings and couldn’t attend it. After he was back, the Scrum Master discovered that the team had been pushed into accepting more work than they could accommodate in that Sprint. What can be done in this situation?
For the past several Sprints, the team completed development on most of the planned issues, but testing could not be completed. The testers felt it was impossible to complete all the tests in the given timebox. How should the Scrum Master proceed?
During a retrospective meeting, the team agreed that their Sprint duration (3 weeks) was insufficient to deliver with good quality. They felt a 4-week Sprint would help reduce the severity of this issue. The Scrum Master asked them to consider reducing the duration to two weeks instead. Why did the Scrum Master make such an unexpected suggestion?
An enterprise architect from a company was conducting a technical review of a product.During the review, he suggested that the team consider using the latest UI framework to enable their web portals for mobile and tablet devices in keeping with the latest trend. He followed up a week later asking the team whether they were doing anything about it. How should the team respond?
Jim is part of a Scrum team and is accused of slacking off by the rest of the team. Apparently, Jim doesn’t collaborate with others, focuses only on his own tasks, and never helps anybody else. The team members want to remove Jim from the team. They approach the Scrum Master with the request. How should the Scrum Master respond?
Kim is a Tech Lead with a product team and is the team’s most senior developer. Her team decides to adopt Scrum. Kim wonders what will happen to her role and asks the coach who is managing the transition. How should the coach respond?
The coach of a Scrum team recommended that the stories be written by hand on an index card rather than entered into the system. Which is the best argument in favor of hand-written stories as compared to stories typed into an Excel sheet or a tool?
A Product Owner was reading out a user story: “… we should make use of REST-based web services to build our SoA layer.” The Scrum Master interrupted and said this is not a good user story. Why did the Scrum Master say this?
During the Sprint retrospective meeting, the Scrum Master ran a quick poll of each team member about how they felt about the achievements of the Sprint. Half the team (mostly the developers) felt the Sprint went really well and the team got a lot done. The other team members (mostly testers and other specialists) felt the work wasn’t complete and the Sprintcould not be considered a success. Based on this information, what should the Scrum Masterfocus on?
A team is planning a release. There are 10 team members and 6 months (about 10,000 working hours) for the release. The team estimates the backlog in ideal hours, which is about 800 hours. The team feels confident that they can accomplish this work. The Scrum Master asks the team and Product Owner to review their assumptions and check again before making the commitment. Why is the Scrum Master doubtful?
A team looked at stories prioritized for the Sprint and feels it can take only 8 out of the 10 stories. The Product Owner wants all the stories to be done because he has an internal demo with the marketing team. The discussion remains deadlocked for several minutes. What is the best way for the Scrum Master to deal with this?
A team was working on a 6-month release and had all the stories lined up, estimated, and assigned to Sprints before they began. During the Sprint review for the second Sprint, the customer recommended a few changes to the reporting dashboards, which would greatly increase their utility. How should the team respond to this?
A team’s velocity for the past 5 Sprints was 45, 55, 63, 38, and 57. The customer wanted a commitment at 90% confidence level about when the team can finish a fixed set of stories. Which of these velocity values should be used?
A team was using planning poker technique to estimate for the first time. The process was taking a very long time. They found that each member was estimating the stories only from their perspective (Development, Testing, Database) and therefore it was hard to reach consensus. How should the Scrum Master help the team?
The team wanted to work on a refactoring task of a size of about 40 hours, but the Product owner was keen on getting a new feature in. How can the Scrum Master help in this case?
The Scrum Master finds that the team members are often blocked by having to wait for user experience designer’s (UED) inputs without which they cannot finalize the screens. The designers are shared across multiple teams and they have a certain lead time in being able to accommodate requests. What is the best way to resolve this issue?
For the past several Sprints, the Scrum Master found that the team’s burn down chart used to slope downward gently, flattening toward the middle of the Sprint, and then rapidly declining to zero on the last day. How should the Scrum Master interpret this trend?
Scrum teams across the organizations measure their velocity in story points completed. The Project Management Office (PMO) wants to collect the velocity data for all teams to set an organizational benchmark. The Scrum Master of a team tells the PMO representative that it is not such a good idea. What might be the Scrum Master’s reasoning?
A customer has outsourced a project to a remote team which uses Scrum. Due to the time zone issues, the users are rarely able to participate in the reviews and give feedback though they would like to. What is the best solution that the Scrum Master can suggest?
A very large product team has been split up into 10 different Scrum teams. The product comprises 10 different subsystems which share functionality. Each team has been finding it difficult to sift through the entire backlog, so they request each team to have its own backlog to make it easier to manage and prioritize. How should the Scrum Master respond to this?
A large product team comprises five different Scrum teams working on the same product.The Scrum Masters meet once a week to synchronize the work. For one of the teams, theScrum Master is out sick. Whom should the team send for the meeting?
A team has been trying to use Scrum for a while, but it has not been working out for them.The main reason is that the team’s backlog is too volatile. The team often gets support tickets to work on in a completely unpredictable and ad-hoc manner. Since the system is business-critical, it is not possible to ignore the tickets. This results in the development Sprints going for a toss as more than 50% of the team’s work is unforeseen. What should the team’s coach recommend?
A team is trying to build a complex product which requires a lot of framework and API level coding before the user visible features can be developed. The team’s Scrum coach insists that every Sprint, including the first one must show visible value to the customer. The Scrum Master disagrees with the coach. Is the Scrum Master right?
The chief product manager is representing a large product team comprising several Scrum teams working in parallel. There are many epics and stories that require multiple projects to be connected and worked on by different teams. The PO would like to implement a tool for managing the backlog, planning, and tracking the project across various teams and give detailed views about progress across the board. What should the Scrum Masters and team members recommend?
A senior member of the Project Management Office in a large company wants to try out Scrum as a methodology. She tries to convince at least one executive to sponsor the program. Everybody questions the need to try out a new methodology when the existing one has been working well. What should be her first step in selling the methodology?
An organization in the middle of a Scrum adoption program has selected a few pilot projects with buy-in from executives. They have appointed Scrum coaches to provide real-time guidance to the teams. Team members have been appointed to the Scrum roles and they have been provided training. What else must be done to make the pilot projects successful?
David is part of a Scrum team. He doesn’t like Scrum and is an active opponent. He makes his displeasure known at every opportunity. He thinks that Scrum is fine for mickey mouse sized projects but doesn’t work for enterprise class projects. He uses every challenge in the team to drive home his point. What can be done about David?
Catherine is an executive in an organization which is practicing Scrum for three months. One of her teams missed the Sprint deliverables for three Sprints in a row. Catherine would liketo speak to a member of the team about what the issues are and how it should beaddressed. Who should be invited to meet with Catherine?
Michael is a DBA and serves five Scrum teams. All the teams have equal need for his time and he also needs about half his time to perform maintenance and tuning on production databases. What is the best way to split up David’s time so that all the teams are able to work with him?
Sean was a developer in a team that transitioned to Scrum about year ago. He is skilled in his trade, knows the product, and has great business insight. His ratings were always top class. He was surprised when his performance rating came down drastically in the current year. His manager told him that the feedback from the rest of the team was not good and Sean was obviously displeased. What should be done about this?
A Scrum team came up with a request to redesign their team space to make it more open and collaborative. The budget requirement was about $20,000. What is the best justification for this expense?